We were contacted by the client, who was a Centra store owner with a portfolio of 12 locations. The customer wanted a fully integrated automated entrance solution. The new store was a redevelopment of a former library, presenting structural and aesthetic challenges.

The Challenge

The project involved repurposing an old public building into a modern convenience store. The key concerns were:

  • Securing the premises in a high-footfall, urban area
  • Ensuring accessibility and customer flow compliance
  • Adhering to fire safety regulations
  • Preserving the existing architectural structure while upgrading functionality
  • Add in retention of heat i.e. draught lobby – allowing easy access while minimising the time door left open

Project Goals

  • Install a secure, regulation-compliant automated entrance
  • Enable smooth customer access and one-way exit flow
  • Integrate new systems with existing roller shutters
  • Achieve a visually appealing, energy-efficient frontage

The Solution

Page Electric worked alongside architects, engineers, contractors, and product manufacturers to develop and deliver a custom access control and automation system.

Products & Services:

Why These Products?

  • Custom Fit: Engineered to suit the unique structural challenges of the old library building
  • Security: The door layout supports a one-way customer flow to deter theft and improve safety
  • Automation & Access: Seamless entry/exit via sensors.
  • Fire Safety Integration: All systems compatible with fire control infrastructure
  • Energy Efficiency e in the newly installed draught lobby

Project Implementation

 

Step by Step Implementation

  1. Initial site survey and consultation
  2. Engineering assessment and custom product selection
  3. Coordination with architect for façade adaptation
  4. Fabrication and delivery of aluminium frames and glazing
  5. Modifications to original design (2-pane to 4-pane glass) for structural safety
  6. Installation of door systems behind pre-installed roller shutters
  7. Final system testing and compliance checks

Timeline

 

Total Duration: 1 month (planning, fabrication and installation)

Project Challenges:

  • Precise sizing and alignment of components due to structural inconsistencies
  • Installing systems behind already-mounted roller shutters added complexity

Standards & Compliance

  • All installations met EN16005 standards for automatic door safety
  • Products aligned with accessibility and fire safety regulations
  • Client-specific safety protocols and building regulation compliance ensured throughout

Results:

  • A secure, efficient, and attractive glazed shopfront
  • Seamless, automated entry and one-way customer flow
  • Enhanced loss prevention via access-controlled design
  • Fully regulation-compliant system tailored to a high-traffic retail environment

 

 